REPORT ON EVALUATION OF KUDANKUALM SITE FOR LCOATION OF NUCLEAR POWER
PLANT PRESENTS IT AS A KILLER PROJECT
http://tshivajirao.blogspot.in/2012/05/why-kudankulam-reactors-are-killers-of.html
http://tshivajirao.blogspot.in/2012/05/why-kudankulam-reactors-are-killers-of.html
Note:This report obtained by Kudankulam anti- nuclear activists from NPCIL under pressure of the RTI Act is presented as rough draft as certain pages were omitted during supply of the copy.
Based on Dianuke website report under the following website.
1.Introduction: The acceptability of a site for locating a
nuclear power plant is dependent not only on site characteristics, related
primarily and directly to safety, but also on a large number of other
aspects which are only indirectly
related to safety. These include the
reliability and stability of the electrical grid, the adequacy of
communications etc.
The siting of nuclear power
plant (NPP) generally involves studies in three stages, namely:
1)Site survey stage: The purpose of a site survey is to identify
lone or more preferred candidate sites after both safety and non-safety
considerations have been taken into account.
This involves the study and investigation of a large region. It results in the rejection of unacceptable
sites, and is followed by systematic screening, and comparison of remaining
sites.
2) Site evaluation stage:
This stage involves the study and investigation of one or more of the
preferred candidate sites to evaluate their acceptability from various
consideration, and in particular from the safety considerations. The site-related design bases are established
at this stage. Subsequent to this a
preliminary safety analysis report is submitted for clearance before site
construction is started.
3) Pre-operational stage: This stage includes studies and
investigations of the selected site after the start of construction and before
the start of operation in order to complete and refine the assessment of site
characteristics and to confirm assumptions made in the safety analysis of the
reactor as a part of the final safety analysis report. The base line data on environment are also
established at this stage.
The stage one is within the scope
of the work of the site selection committee.
The present committee aims to have a preliminary evaluation of the
feasibility of a site mainly from safety considerations and ensure that the
plant site combination does not constitute an unacceptable risk. However, in ivew of the fact that some
non-safety considerations may affect safety related aspects, such items also
have to be studied. It is to be
understood that the present committee has evaluated the site from screening
considerations. The site related design
parameters/bases are to be established at appropriate stages. The review is based on the available
information on population and industrial growth and other proposed facilities
at and around the site in addition to safety related aspects like seismo-tectonic
environment, geology, hydrology, extreme meteorological Phenomenon etc. The site is evaluated from the following
considerations.
1.
Effect of the region of the site on the plant 2. Effect of the plant on the region
3.
Population considerations.
While the first of the above
factors decide the safety of the plant due to site related natural and
man-induced events, the second factor influences the potential radiological
impact from the plant on the environment.
Population consideration is important for emergency planning.
The acceptability of a site
for a particular NPP depends on the existence of engineering solution to site
related problems which gives assurance that the proposed plant can be built and
operated within acceptably low risk to the population of the region.
IAEA guidelines (1,2) have
been kept in mind for the site evaluation.
2. REVIEW FOR THE SUITABILITY OF THE SITE AT KUDANKULAM
2.1 GENERAL CONSIDERATIONS 2.1.1
SAFETY-RELATED ASPECTS
Potential site-specific
natural hazards and man-induced events have been evaluated for initial
appraisal of their impact on the plant design and the enigneerability under the
given circumstances. Subsequently, these
studies form the design bases.
Among the natural hazards, the
following aspects as relevant to site have been studied.
i)
Surface faulting ii)Seismicity iii)Suitability of subsurface material
iv)
Flood and
v)Extreme meteorological
phenomena (e.g cyclone)
Because of rocky substrata
slope instability, soil liquefaction, surface collapse, subsidence or uplift
are not applicable for the present site.
Man-induced events include
accidents due to
i)
Air traffic ii)Vehicular road traffic
ii)
Industrial and Military activities in the
immediate vicinity of the site.
Capability of dispersion in
air and water are studied for possible radiological impact on environment. The
availability of adequate cooling water supply for the ultimate Heat Sink is the
central safety issue. Feasibility of
implementing effective emergency actions has also been considered.
2.1.2 NON-SAFETY CONSIDERATIONS
(Economic, Technical, Environmental
and Social Aspects)
These are primarily related to
engineering feasibility. However, some
of the factors may indirectly be related to the safety of the NPP.
The factors considered are: i)Electricity network ii)Availability of cooling water iii) Transport
routes
iv) Topography v)Industrial
support at site vi) Non-radiological
impact on the environment (e.g.. chemical and thermal pollution, industrial
growth and its impact etc.)
2.1.3 OBSERVATIONS OF THE
COMMITTEE
The committee has studied all
site related data submitted by NPC (3,4,5) and has, in accordance with the
criteria mentioned above, made a review of the suitability of the Kudankulam
site for locating nuclear power station having two units of 1000 MWe VVER
reactor.
The review findings are
presented in Tables I and II
3.0 ACTIONS TO BE TAKEN:
The committee recommends that the following
actions should be taken at appropriate stages.
3.1. ASPECTS RELATED TO SITE
1)
ODC committee of NPC to evaluate suitability of
transportation of ODC at design stage
2)
Maximum Flood Level should be estimated
accurately considering IAEA safety Guide 50-SG-S10B. Revised report of CWPRS should be submitted
to Design Safety Committee.
3)
Analysis for the quality of construction water
is to be carried out.
4)
In order to enhance additional reliability for
water Supply, which is essential for functioning of various safety systems of
the reactor, intake well at Pechiparai Dam should be provided at lower
elevation than the minimum draw-down level of the reservoir. However, it should be ensured by proper
management of water distribution that the water level is maintained above this
minimum level.
5)
Adequate storage of fresh water for prolonged
safe shutdown of the reactors is to be provided within plant boundary for
safety related systems. Ground water
source should be explored.
6)
Environmental Survey laboratory should be set up
at site and instruments are to be installed at site to collect meteorological
data and background radiation.
7)
Site related design considerations such as
seismic aspects, etc are to be established before submission of PSAR.
8)
The committee has been informed that detail
subsoil investigations have been carried out (12). Bore-hole investigations are to be carried
out at the proposed location of various buildings and structures. The report should be forwarded to design
group for taking into account at the time of actual design.
9)
Power evacuation studies particularly that
influence the plant grid interaction should be persued. Feasibility of operation on islanding mode
may be studied in collaboration with CEA.
In addition availability of a reliable (dedicated) startup power source
of adequate capacity should be examined.
10)
Stipulations made by various state and central
authorities in giving clearance, should be met.
In addition, plantation in the area under control of the project should
be taken up along with site development.
11)
Tamilnadu
legislation to control population growth beyond natural growth within the
sterilized zone is to be implemented.
12)
Termination of the lease in 1994 for lime stone
quarry.
3.2 ASPECTS RELATED TO DESIGN:
1.
Radiological impact should be assessed with
proper source terms and relevant dispersion characteristics of the site. Dose limits prescribed should be met at a
distance of 1.6km in event of greater exclusion radius adopted by NPC.
2.
Stack height to be checked by Health Physics
Division,BARC, considering topography and dispersion characteristics.
3.
Model
studies should be taken up for intake and outfall structure for thermal pollution
and recirculation.
4.
Studies on Biofouling and jelly-fish etc. that
may affect the water supply should be taken up.
5.
Studies on accretion/erosion rate around the
plant site should be carried out. If
required, proper protection should be provided.
6.
Design should be engineered to meet site related
design basis events.
7.
Atleast
two evacuation routes from plant site during an emergency should be provided.
4.0 RECOMMENDATIONS:
The committee is of the
opinion that Kudankulam site meets the major criteria for siting 2 x 1000 MWe
VVER units. The Committee at the same
time recommends that the observations made in the preface and the actions
recommended in Section 3 above need to be implemented at appropriate stages.
REFERENCES
1.
IAEA – Code of Practice on Safety in Nuclear
Power Plant Siting. IAEA Safety Series
No.50-C-S International Atomic Energy Agency, Vienna, 1979
2.
Site Survey for Nuclear Power Plants. IAEA Safety series No. 50-SG-S9. IAEA(1984)
3.
Environmental data on proposed Kudankulam site
for submission to Tamilnadu Pollution Control Board for 2 x 1000 MWe VVER
nuclear power station.
4.
Write up on Kudankulam site – DAE
5.
Siting data in AERB standard format. (Received from NPC vide letter
NPC/KK/24/1032, dt.7-3-89
6.
Layout of main plant building for 2 x 1000 MWe
VVER project at Kudankulam
7.
CWPRS Pune Report: “Safe Grade Elevation for the
proposed nuclear power station at Kudankulam,
Tamilnadu
8.
Draft report on Earthquake design basis for
Kudankulam site, DAE, 1988 – A.K Ghosh and DC Banerjee.
9.
Appendix to Part-I of Site Selection Committee
report
10.
Power Transmission system for Kudankulam Atomic
Power Project -CEA report
11.
Letter NPC/KK/24 dated 16-3-89 received from NPC
12.
Brief note from NPC on “Geological setup of
Kudankulam site”.
T A B L E -1
SALIENT FEATURES
OF KUDANKULAM SITE CONSIDERED DURING SITE EVALUATION
S.No.
|
Site characteristics
Influencing the NPP
|
Specification/Desirable
Characteristics
|
Observations for Kudankulam
site
|
Remarks
|
1
|
Topography
|
Plain topography
|
Plain
topography-elevation+3m to 45m above MSL.
Area measuring 1Km to 2Km available (3), (6)
|
Terrain suitable sufficient
land available for future expansion
|
2
|
Accessibility
i) Nearest Broadgauge rail
head
|
Kanyakumari(27Km), Valliyur
(27Km)
|
Recommendation for ODC
transport
1)All consignments/equipments
with weight (30Ton: USSR-tutitorin by ship Tuticorin-site: by road or on
barges by sea route
2) All consignments (30 ton
USSR-site: by ship and barges. To be unloaded at jetty within the plant
|
|
ii)Nearest National Highway
|
NH7 at Kanyakumari 27Km,
Valliyur 27Km,
|
|||
iii) Nearest Seaport
|
Tuticorin (100Km)
|
|||
iv) Nearest district road
|
Coastal road 4Km
|
|||
3
|
Construction Facilities
i)Construction materials
|
Coarse aggregates available
at Anjugrarer (4km). Sand available at
Ratucenathjewari road (7km) Bricks
available at Panagudi (27km)
|
More sources will be
established at construction stage.
|
|
ii)Construction power
|
26KVA +2 KVA for township
|
Panagudi sub-station
(27Km) - 110KV line exists. 110KV line
from Kodyar power station is also being considered.
|
||
iii)Construction water
|
3.5 cu.sec (350 cu.m per
hour
|
Initially limited supply to
be tapped from ground water sources.
Subsequently the demand will be met from Pechiparai dam
|
Quality of construction
water is likely to be acceptable.
Analysis of water will be carried out.
|
|
iv)Infrastructure facilities
(e.g minor workshop etc)
|
Nagercoil (30km) and
Tuticorin (100km)
|
|||
4
|
Availability of Power Supply
and Transmission Lines
i)Start-up Power
|
50KVA per unit
|
Available from main state
grid and Tuticorin Thermal Power Station Plant (630MW) 220KV line to be drawn
from Tuticorin.
|
|
ii)Power evacuation scheme
|
Feasible as per preliminary
study conducted by CEA. Detail study
is in progress
|
Present grid capacity 12832
MWe. Nuclear 470MWe. Projected
capacity in 1995 will be 27541MWe.
Nuclear 1910 MWe
|
||
5
|
Availability of Water
i)Condenser cooling
|
6000 Cu sec
(on once-through basis)
|
Sea water cooling on
once-through basis silt content:60-100 ppm Particle size75 microns.Temperature:26-29
oC
|
No constraint. Titanium
tubes will be used. Study on biofouling
and jelly fish that may affect the water supply will be taken at design
stage. Model study will be taken up
for intake and outfall structure(5)
|
ii)Fresh water for make-up
and domestic use
|
10 cu sec
|
Assured by State
Government. One pipeline from
Pechiparai dam (at 65km) to be laid. pH:7.
Dissolved solids:25mg/litre,
Suspended solids:negligible, Turbidity:5mg/l (5)
|
Dam storage 4.45 TMC ft.
Dead storage can account for 3 years drought (5)
|
|
6
|
Township
|
400 acres
|
400 acres of land identified
near Chettikulam village about 7km from the site (3)
|
TABLE-2 SITE CHARACTERISTICS AFFECTING SAFETY OF
PLANT
S.No.
|
Site
Characteristics Influencing the NPP
|
Specification/Desirable
Characteristics
|
Observations for
Kudankulam site
|
Remarks
|
1
|
Geology
i)Foundation conditions
depths of bed rock and type
|
Bed rock at 5-16m below
ground. Biotite granite genesis with lenticular bodies of charnockites or
quartzites
|
||
ii) Strength
|
Maximum intensity of loading
6kg/sq.cm at RB
|
Dry strength : 650kg/sq.cm
Wet strength: 450 kg/sq.cm
(5)
|
||
iii)Ground water
|
Below 1m
|
5-8 m below ground –
gradient towards sea (5)
|
||
2.
|
Natural events:
i)Coastal erosion
|
Erosion insignificant with
respect to life of station. Nearest main plant structure from shore about
120m away from the sea base line
|
Layout for the main plant
still under consideration figure of 120 tons estimate on the basis on 7 ton
as the ground elevation at main plant building.
|
|
ii)Flood
|
Maximum flood level
considering tidal range wave run-up and maximum stage surge 5.9m above chart
datam of 0.0 Exposed structures placed well above this level. (7)
|
Grade level around Reactor
Building will be above 7m from MSL.
Revised report on MFL from
CWPRS awaited. Grade elevation will be
changed if necessary.
|
||
iii)Tsunami
|
Not significant as per preliminary
report of CWPRS
|
1m height of wave considered
due to tsunami effect.
|
||
iv)Wind, storm, Cyclone
|
Maximum speed of
storm:112km/hr. Storm surge accounted for in flooding. Exceedance probability
5% as per preliminary repsort from CWPRS.
|
Engineering capability to
design for wind load exists.
|
||
v)Slope instability
|
Not applicable for rocky
substrata
|
|||
Vi)Soil liquefaction
|
Not applicable for rocky
substrata
|
|||
vii)Seismotectonic
environment
|
No active fault within 5km
of NPP. Engineering capability for stipulated earthquake acceleration should
be possible
|
No active fault within 5km.
Site is in seismic zoneII as per IS 1893; 1984. Nearest epicenter at
Trivandrum (90km) earthquake in the region.
Magnitude 6 at Coimbatore (8
Feb, 1900) (300 km) Estimated peak horizontal acceleration for SSE is 0.15g
and for OBE is 0.06g.
|
Engineering capability to
design for such earthquake loads exists. Seismic evaluation report finalized after
discussion with GSI and Soviet Specialists.
Further ground checks have confirmed the assumptions regarding the
nearest
|
|
PAGE – 13 MISSING
|
||||
5.
|
Use of Land
|
Within in the exclusion
zone: 34% of area lies in sea.
Remaining 650-750 ha of land (no forest), mostly private owned, is
barren and unirrigated/poorly cultivable.
Extremely limited agriculture.
Annual yield: 20 tons of millet
and 2 tons of cotton
Within 10km radius area: 60%
of area lies in Sea. Remaining land is barren or used for agriculture. Annual yield:Paddy 14400 tons, millet 4300
tons, chillir 3000 tonnes, tobacco 380 tons, pulses 830 tons, cotton 250
tons, oil seeds 70 tons (4)
|
A lime stone quarry of about
70 acres falls within the sterilized zone.
The lease for this area expires in 1994. Termination of the lease beyond the period
has been requested.
|
|
6.
|
Use of Water
|
Ground water, limited in
supply is used for drinking andhas a gradient towards the sea. No salt pans within 5km. The degree of
development of fisheries is as common as in a coastal belt. In the near by area, indinthakarai,
Koothapuzh, Koothankuzhi and Perurranal are the fishing villages within 20km
and annual fish produce of about 4000 tons in the area is reported. About 3900 fisherman in these villages are
engaged infishing as per information furnished in 1982. At Chinneruttar near Kanyakumari, a fishing
harbor is being developed. (4)
|
||
7.
|
Disposal of Radioactive
waste from the NPP
i)Solid waste
|
Low level solid waste to be
buried within exclusion zone in leak-proof RCC vaults/trenches/tile
holes. 160-180 m cu per year of cemented waste including spent absorption
materials, 40m cu/yr of compacted waste and 5 m cu/yr of cemented ash will be
generated from one reactor (5)
|
Borewells surrounding the
solid waste burial area will be provided for monitoring migration of
activities.
|
|
ii)Liquid waste
|
To be diluted to 2 x 10E-7
micro Ci/ml when discharged into the sea.
|
Most of the radioactivity in
the liquid is removed in the Ion exchange resin and as evaporator
concentrate. After above processing
the liquid effluent from two units is estimated as 6000 m Cu/year with
activity levels lesser or equal to 10E-9 Ci/l. This will be further diluted by condenser
cooling water to meet the limits allowed by AERB
|
6000 cusecs of sea water available
for dilution while sea water less than 1 cusec required to achieve the
specified limits.
|
|
iii)Gas release
|
Stack height is 100m. Use of
high efficiency (0.3 micron) particulate absolute filter will help to comply
with authorized limits for particulate activity. The estimated gaseous
discharges from two units as following.
Nuclides Avg daily
Releases
Ci/day
Noble gases-- 2220
I-131 30 x 10E-4
Long life 0.012
Nuclides
Short life 0.26
nuclides
|
It is understood that
specific detailed information regarding waste and radioactive releases will
be available along with PSAR for review
|
||
8
|
Radiological
Impact
i)during normal operation
|
AERB prescribed limits
|
Based on releases vide
para7, preliminary estimates indicate very low dose rates 11.24 mrem/yr to
the individual at 1.6km exclusion radius.
Both the water and air routes have been considered in the above
estimates.
|
|
ii)During design basis
accident conditions
|
10 rem for whole body, 50
rem for child thyroid at exclusion radius
|
For all design basis
accidents adequate engineering safety features shall be provided to meet the specified requirements.
|
DBA calculations will be
carried out at the design stage
|
|
9
|
Thermal Pollution
|
Not significant. Intake and outfall will be well
separated. Depth of sea water and
large dilution due to sea will avoid thermal pollution
|
Model studies will be carried
out at CWPRS Pune. The requirements of
Tamilnadu pollution Control Board should be met
|
|
10
|
Storage and Transportation
of Fresh and spent fuel
|
Space for storage of fresh
fuel for 5 years plus one core charge will be provided. Each unit layout can store spent fuel of 5
reactor years in the spent fuel pool located inside the containment. Besides this space will be available to
unload one core inventory.
|
50 ton of spent fuel will be
discharged annually from the 2 reactors.
After adequate cooling inside the pool, it will be shipped to Soviet
Union by sea route in hermatically sealed casks. Special jetty provided within the plant
area will be used for transfer of cask to the Soviet ships so that spent fuel
remains within plant boundary at all stages during the process of shipment of
irradiated.
|
|
11
|
Fuel Reprocessing facility
|
Reprocessing not planned at
this site
|
||
12.
|
Population considerations
i) Population within 2km
radius exclusion zone
|
No habitation
|
No resident population
|
|
ii)Population within 5km
radius sterilized zone
|
Less than 26,000 population
density (2/3 state average.
|
Total population:15,000, 3
villages in this area Kudankulam, Idinthakarai and Erukkanatharam
|
Tamilnadu legislation to
control population growth beyond natural growth within the sterilized zone to
be implemented.
|
|
iii)Population within 10km
radius zone
|
No center >10,000
|
No population centre with
more than 10,000 people. total
population 40,842 (1961 census). Population density:130 persons/sq.km
|
||
iv)Population within 30km
radius zone
|
No center >1,00,000
|
No population center with
more than 1 lakh people. 11 centers
have population more than 10,000
Nagercoil (at 30 km has a population of 1,71,641.
|
||
v) Population within 50km
radius zone
|
33 population centers with
population more than 10,000 (4)
|
|||
13
|
Emergency Preparedness
Considerations
|
3 routes exist for possible
evacuation. Schools and other public buildings
exist for adequate temporary shelter, nagercoil (30km), Tirunelveli (100km)
and Tuticorin (100km) can provide rehabilitation
medical facilities and administrative support
|
Draft proposal on off-site
emergency preparedness plans already submitted to AERB.
|
|
14.
|
Additional Statutory requirements of the
Central and State Government
|
Clearance for the following
has been obtained:
Tamilnadu pollution control
Board, Shore protection committee of Tamilnadu Government, State Committee on
Environment, Minister of Environment and Forests (Government of India)
|
Stipulations made in the
clearance documents should be adhered to.
|
No comments:
Post a Comment