COMMENTS BY
Prof.T.Shivaji Rao,
Director, Center for Environmental Studies, GITAM University, Visakhapatnam
A5 - INTERIM REPORT
OF TASK FORCE
ON SAFETY EVALUATION OF THE SYSTEMS OF KKNPP POST
FUKUSHIMA EVENT
1.0 Introduction
1.1 General:
Kudankulam
Nuclear Power Project (KKNPP) consisting of two VVER-1000 type of units having
1000 MWe rating each is under advanced stage of completion at Kudankulam in
Tirunelveli district of Tamil Nadu. Construction activities at site started on
31st March 2002 with first pour of concrete of Unit -1. Unit -1 is presently
undergoing prestart up commissioning activities and construction and erection
works of unit-2 is nearing completion. Two units at KKNPP are being implemented
with technical assistance of Russian Federation (RF) as per the Inter
Government Agreement (IGA) between the two countries. As per the agreement,
design and supply of all major equipments are done by RF while construction,
erection, commissioning and operation are being carried out by Indian side.
KKNPP design incorporates advanced safety features complying with current
standards of redundancy, reliability, independence and prevention of common
cause failures in its safety systems. Design takes care of Anticipated
Operational Occurrences (AOO), Design Basis accidents (DBA) and Beyond Design
Basis Accidents (BDBA) like Station Black Out (SBO), Anticipated Transients
Without Scram (ATWS), metal water reaction in the reactor core and provision of
core catcher to take care of core degradation. The design includes provisions
for withstanding external events like earthquake, tsunami/storm, tidal waves,
cyclones, shock waves, aircraft impact on main buildings and fire.
1.2 In light of the accident
at Fukushima, Japan, initiated by natural phenomenon, the Task Force
constituted, has reviewed the capability of KKNPP to withstand and mitigate
extreme natural phenomenon which have very low probability of
occurrence
but potential for loss of significant operational and safety systems In view of
the advanced safety features including passive decay heat removal system, the
plant has very high capability to withstand severe natural events with margins
available from design input parameters. However in order to enhance the safety
levels further and building additional defense in depth the task force has
recommended some short term and long term measures.
1.3 Site characteristics:
Kudankulam
NPP is located close to the equator at the shore of Gulf of Mannar. The South
Eastern coast where Kudankulam NPP is located can experience cyclonic storms.
Five storms with maximum wind speeds ranging from 17 m/s to 31.7 m/s were
recorded in this region during the period from 1891 to 1986. One of the storms
had passed near to the KKNPP construction site, while two of the storms,
including the strongest one passed 100 km north of the site. High and low tides
influence the sea water levels. The maximum observed high tide is plus 0.62 m
(MSL), while minimum observed low tide is minus 0.49 m (MSL). The tidal range
is about 1 m. The local mean sea level (LMSL) near Kudankulam NPP is minus 0.03
m with reference to average mean sea level. The KKNPP is situated in an area
with an expected earthquake intensity of up to V on Modified Mercalli Intensity
Scale (MMI scale) and falls in Zone-2 seismic category. The strongest
earthquake near this area and within the Indian peninsula is the Coimbatore
earthquake of February 08, 1900. The epicentral intensity has been reported as
VII (MMI scale) and Indian Meteorological Division (IMD) has estimated its
magnitude to be equal to 6.0 on the Richter scale. The earthquake epicenter was
situated at a radial distance of 300 km from the KKNPP site.
The
nearest epicenter of a recorded earthquake was located near Trivandrum, which
is situated at a distance of 88 km north-north-west of the Kudankulam NPP site,
where two earthquakes of V (MMI scale) intensity, corresponding to 4.3
magnitude on Richter scale, were recorded. Different buildings in the plant are
built taking into account the above natural phenomenon.
2.0 Scope and Objective:
The
objective of this Task Force is to review the consequences of occurrence of a
similar situation like Fukushima Daiichi NPP postulated at KKNPP resulting in
the unavailability of electric power and the designed water supply route and to
recommend augmentation measures to mitigate the situation. This includes:
1.
Evaluate the capabilities of the systems
2.
Identify the required augmentation measures and infrastructure facilities,
hook-up points to mitigate this beyond design basis scenarios.
3.
Review of Emergency Operating Procedures (EOPs).
3.0 Design Features of KKNPP:
3.1 General:
VVER
types of reactors are Pressurised Water Reactors (PWR), consisting of primary
and secondary circuits. Primary circuit comprises of a vertical reactor, four
coolant recirculation loops each having a coolant recirculation pump and a
steam generator (horizontal) and a pressuriser connected to one of the coolant
loops. Main technical parameters of KKNPP are given in the following table:
Parameter
|
Value
|
Reactor
nominal thermal power, MW
|
3000
|
Reactor
thermal power considered in design,
|
3120
|
Primary
coolant
|
Light
Water (Borated)
|
Primary
coolant inventory, m3
|
290
|
Primary
system design pressure, MPa
|
17.64
|
Coolant
pressure at the core outlet, absolute, MPa
|
15.7
|
Coolant
temperature at the reactor inlet, ºC
|
291
|
Coolant
temperature at the reactor outlet, ºC
|
321
|
Coolant
flow rate in one loop, m3/h
|
21500
|
Coolant
flow rate through the reactor, m3/h
|
86000
|
Pressuriser
volume, m3
|
79
|
Number
of fuel assemblies
|
163
|
Average
fuel enrichment, % during equilibrium cycle
|
3.6
|
Av.
Fuel burn up, MW days/kg of uranium
|
43
|
Operation
time at nominal power, h
|
7000
|
Number
of control and protection absorber rods
|
121
(max)
|
Steam
Generator (SG) capacity, t/h( for each SG)
|
1470
|
Steam
pressure at nominal load , MPa
|
6.27
|
Temperature
of generated steam at nominal load, ºC
|
278.5
|
Feed
water temperature under nominal condition, ºC
|
220
|
3.2 Safety Features:
On
initiation of emergency protection system, automatic reactor trip takes place
and reactor becomes subcritical due to simultaneous gravity drop of all the
Control and Protection System Absorber Rods (CPSAR) into the core on
de-energisation of the holding electromagnets. There are also provisions for
injection of concentrated boric acid in to the primary coolant system by
Emergency Boron Injection System (EBIS) using positive displacement pumps
supplied by Group-II Emergency Power Supply and also Quick Boron Injection System
(QBIS) which injects concentrated boric acid to the Reactor Coolant System
(RCS). Safety Systems are provided to ensure the core cooling under
various conditions of Postulated Initiating Event (PIE) considered in the
design, which includes Anticipated Operational Occurrences (AOO), Design Basis
Accidents (DBA) and most of the BDBAs. Salient features of the safety system
design are:
ü Four 100% capacity trains for redundancy.
ü Each train has its own emergency power supply backed
up by Diesel Generator (DG) sets and battery banks.
ü Active systems backed up by passive systems.
ü Physical separation of the four trains to preclude any
common cause failure.
ü Systems are provided for BDBA conditions also.
All
these safety equipments are located in safety building (UKA) located below
Reactor Building (RB). This building is seismic category-1 and protected with
double seal water leak tight doors. Containment Systems are provided for
confinement of radioactivity during an accident condition. Salient features of
the containment system design are:
ü Double Containment
ü Primary Containment designed for LOCA peak pressure of
0.4MPa.
ü Containment spray system for pressure control.
ü Secondary Containment designed for various external
effects, such as missile attack, aircraft crash, shock waves, etc.
ü Hydrogen re-combiners for combustible gas control
inside the primary containment.
ü Core catcher for confining and cooling the molten core
under severe accident conditions.
Safety
systems provided at KK NPP is summarized in the following table:
Function
|
Active Systems
|
Passive Systems
|
Reactor
shutdown
|
Emergency
Boron Injection System or EBIS (for ATWS)
|
CPSARs
Quick Boron Injection System or QBIS (for ATWS)
|
Decay
Heat Removal
|
Steam
generator Emergency cool down system or SGECD (JNB 10-40)
High
pressure boron
injection
system (JND 10-40)
Emergency
and planned cool down and fuel pool cooling system (JNA 10-40) Component
cooling system (KAA 10-40) Essential sea water cooling system (PEB 10-40)
Emergency power supply system ( Group-II)
|
1st
stage accumulators 2nd stage accumulators (for BDBA)
Passive
Heat Removal System-
PHRS
(JNB 50-80) (for BDBA) Emergency Power Supply System (Group- I) for 2
Hrs Emergency Power Supply System for 24 Hrs (Gr-I) (for BDBA)
|
Confinement
of radioactivity
|
Containment
spray system (JMN 10-40) Containment Isolation System
|
Primary
containment Secondary containment Core catcher (for BDBA) Passive
hydrogen re-combiners (for BDBA) Hydrogen monitoring system Annulus
passive filtration system (for BDBA)
|
3.3 Emergency Power Supply Systems (EPSS):
KKNPP
is connected to the grid through two separate systems of 400KV and 220 KV. Each
of the four safety train has its own dedicated EPSS and control systems
comprising of a 100% capacity DG sets, 6 KV, 380V, 220V AC/DC switchgear,
battery banks. All the equipments are housed inside independent buildings and
the pipelines and cables are laid through independent dedicated concrete
tunnels. These buildings are seismic category-1 and protected with double seal
leak tight doors which will also prevent water intrusion. Grade level of the
EPSS building is 9.3 m above MSL.
3.4 Sea Water Cooling System For Emergency Loads:
All
the heat exchangers of the Emergency Core Cooling System (ECCS) and DG sets are
cooled by seawater supplied from sea water system for essential loads. There are
four pumps; one for each safety train. Each pump is located in independent
building near main pump house and power supplied from respective EPSS. Pipe
lines and cables are laid through independent and separate concrete tunnels.
These buildings are seismic category-1 and protected with double seal leak
tight doors which will also prevent water intrusion. Grade level of this
building is 7.65 m above MSL.
3.5 Spent Fuel Storage And Cooling System:
In
KKNPP, Spent Fuel Pool (SFP) is located inside the primary containment adjacent
to reactor cavity; bottom of the pool is +12.5m. It has the capacity to store
582 number of spent fuel assemblies. Water inventory inside the SFP is about
1500 m3, out of which 500 m3 is meant for ECCS operation. Cooling of the SFP is
done using one train of Emergency and planned cool down and fuel pool cooling
system (JNA 10-40). SFP make up is done using spent fuel pool makeup system
(FAL).
3.6 Seismic Design:
All
the safety related main plant buildings have been designed as seismic
category-I. The polar cranes in the reactor buildings are provided with seismic
arrestors.
Design Basis Earthquake (DBE): Estimated
intensities of earthquakes and peak ground accelerations at the site for the
design-basis earthquake and ultimate design-basis earthquake are given in the
following table. It can be seen that substantial margins are available between
design
basis earthquake values and ultimate design basis earthquake values.
|
Peak ground acceleration (g)
|
Earthquake intensity at the site (MMI )
|
||||
|
Horizontal
|
Vertical
|
|
|||
Ultimate
design-basis earthquake
|
|
0.11
|
VII
|
|||
Design-basis
earthquake
|
0.05
|
0.036
|
V
|
3.7 Seismic instrumentation and protection:
The
seismic instrumentation has been designed for monitoring seismic activity and
providing automatic reactor shutdown in case of occurrence of an earthquake
having free ground accelerations of 0.036g for the vertical component and 0.05g
for the horizontal component. When the acceleration reaches 0.025g recording is
initiated. Two sets of seismic sensors each set containing three accelerometers
are provided for generating Emergency Protection (EP) signals. These sensors
are positioned on the base slab of the reactor building.
3.8 Flood design and Important plant levels and locations:
Design Basis Flood Level The
design maximum sea level with a 0.01 % probability (that occurs once every
10000 years) is estimated as plus 5.30m (MSL). The design minimum sea level of
the same probability is minus 1.72m (MSL). Elevations and locations of various
buildings are given in the table. A sketch showing the relative elevations of
various structures is also given. The shore protection structure rises upto 8
meters height above mean sea level and hence will protect the site from direct
impact from tsunami waves. The water level experienced at site during the
December 26, 2004 tsunami triggered by earthquake of 9.2 magnitudes at Sumatra
was only about 2.2 meters above mean sea level.
Table- Important Elevations for KKNPP Description
|
Elevations in meters above MSL
|
Margin available Meters from DFL
|
Reactor
Building ground floor
|
+8.7
m
|
3.26
|
Spent
fuel pool - bottom
|
+12.5
m from RB floor (+21.2m above MSL)
|
15.76
|
Spent
fuel pool - normal water level
|
+30.85
m from RB floor (+39.55 above MSL)
|
33.41
|
Safety
DG sets (4 per unit) in UKD building(sealed building)
|
+9.3
m
|
3.86
|
Reliable
PS DG sets (common for both units) (sealed building)
|
+8.2
m
|
2.76
|
Diesel
day tanks in DG building , 15 m3 , 8 Hrs FL capacity in UKD building (sealed
building)
|
+14.1
m
|
8.66
|
Group-II
switch gear of safety trains in UKD building (sealed building)
|
+9.3
m
|
3.86
|
Group-I
Battery Bank for 2 hrs (sealed building)
|
+12.9
m
|
7.46
|
Group-I
Battery Bank for 24 hrs (SBO Batteries) (sealed building)
|
+16.5
m
|
11.06
|
Group-I
switch gear of safety trains in UKD building (sealed building)
|
+9.3m
|
3.86
|
Safety
trains control instruments room in UKD (sealed building)
|
+16.5m
|
11.06
|
PHRS
Heat exchangers
|
+
51.8m
|
46.31
|
Main
control room in UKC
|
+
29.7 m
|
24.26
|
Supplementary
Control room(shielded and sealed)
|
+9.7m
|
4.26
|
In
addition to location at higher elevations, all the safety related buildings are
closed with double gasket leak tight doors. Hence water entry into these
buildings is extremely remote even in case of sea water level surge reaching
upto their elevations.
3.9 Existing On Site Water Inventory:
Source
of water for the plant operations is an onsite sea water desalination plant.
This plant has the capacity (3x100 m3/Hr) to meet the total requirement for
plant operation and domestic water of unit 1&2. Water from the desalination
plant is further de-ionized at the De-Mineralized (DM) plant before using in
the main plant. Water produced at the desalination plant/DM plant is stored at
various tanks as shown in the table.
Sr. No.
|
Description
|
Capacity (m3)
|
Location
|
1
|
DM
water storage tanks in DM Plant
|
630x2=1260
160x2=320 (1580) (common to Unit 1 &2)
|
+8.5m
in DM Plant
|
2
|
DM
water storage tank LCP near TB
|
1000
per unit
|
+8.1
near TB
|
3
|
Deaerator
|
250
|
Inside
TB
|
4
|
Emergency
water storage in SFP
|
500
|
Inside
RB(SSE qualified)
|
5
|
ECCS
tank stage-1
|
4x60=240
|
-do-
|
6
|
ECCS
tank stage-2
|
8x120=960
|
Inside
RB(SSE qualified)
|
7
|
Distillate
storage tanks KBC
|
160x2=320
630x2=1260 (Total 1580)
|
Inside
RAB(OBE qualified)
|
8
|
Boric
acid tanks KBD
|
160x2=320
|
Inside
RAB(OBEqualified)
|
9
|
SFP
filling tanks
|
400x2=800
|
Inside
RAB(OBEqualified)
|
10
|
Firewater
tank
|
1000x2=2000
|
+8.1m
near Fire station
|
11
|
Domestic
water tank
|
550
(O/H tank) 275x3=875 (U/G tank)
|
+44m
Outside Operating Island
|
12
|
Desalination
Plant
|
630x1
160x1
|
+8.5m
Outside Operating Island
|
Out
of the tanks mentioned against S.Nos. 1, 2 & 7 in the above table, except
for two 160 m3 capacity tanks at D.M. plant other tanks are designed for
seismic category II (OBE). The other two 160 m3 tanks are category III
conforming to codel design.
3.10 Decay heat removal provisions:
Core cooling during loss of Group –III power supply
During
loss of Group-III power conditions, reactor is shutdown automatically and core
cooling is achieved by natural circulation of primary coolant system through
steam generators. Heat removal from SG takes place initially through Page 16 of 24
atmospheric
discharge valves and PHRS. After starting of the DG sets, closed loop system of
SGECD comes into operation. As both PHRS and SGECD are closed loop systems,
there is no need of SG inventory replenishment. SGECD pumps are supplied with
Group-II EPSS. However, auxiliary FW pumps powered from common station DG sets
will be available for SG level makeup. Normal cool down rate of reactor using
SGECD is 30 deg C/Hr and fast cooling can be done at 60 deg C/Hr. After cooling
down of RCS to 120-130 deg C, further cooling of reactor coolant system is done
using one train of emergency cool down system JNA. If required primary make up
can be done using following methods: By using make up pumps when Gr-3/Gr-2
reliable supply is available. By using high pressure emergency boron injection
pumps when Gr-3/Gr-2 supply is available. By using high pressure boron
injection pumps at 6.5 MPa when Gr-3/Gr-2 supply is available. By using 1st stage
ECCS accumulators at 6.0 MPa when Gr-3/Gr-2 supply is not available. By using 2nd
stage ECCS accumulators at 1.5 MPa when Gr-3/Gr-2 supply not available. Water
makeup to steam generators can be done from deaerator storage tank when
Gr-3/Gr-2 power is available.
3.11 Core cooling during SBO:
In
case of simultaneous loss of Gr-III and Gr-II power supply reactor is shutdown
automatically and core cooling is achieved by natural circulation of primary
coolant system through steam generators. Heat removal from SG takes place
initially through atmospheric discharge valves and PHRS. On sensing low level
in SG closure of Fast Steam Isolating Valve (FSIV) will take place and SG
cooling will continue using PHRS. As per the safety analysis reports, primary
coolant temperature &pressure comes down to 165º C and 3.4 MPa after 24
hrs. If required primary make up can be done using following methods: By using
1st stage ECCS accumulators at 6.0 MPa when Gr-3/Gr-2 supply not available. By
using 2nd stage ECCS accumulators at 1.5 MPa when Gr-3/Gr-2 supply not
available.
3.12 Design Basis Accident (DBA):
Safety
analysis of various design basis accidents have been carried out including loss
of coolant accidents (LOCA) covering a spectrum of primary coolant pipe break
size from 100mm to 850mm. Results of these analysis have proved that acceptance
criteria is met for all the conditions. Containment spray system is available
for post accident depressurization provided with Group II power. (JMN 40).
After containment pressure reduces, provision for controlled post accident
purification through filters and purge to stack, using fans having Group II
power supply, is also available.
3.13 Beyond Design Basis Accidents (BDBA):
Safety
analysis of various beyond design basis accidents have been carried out
including loss of coolant accidents (LOCA) with Station Black Out (SBO) for 24
hrs and Anticipated Transient Without Scram (ATWS). Results of these analyses
have proved that acceptance criteria are met for all the conditions. Monitoring
of all the important parameters for core, radiation monitoring, reactor coolant
system and containment are available through Group-1 Emergency Power Supply
System (EPSS) i.e. 24hr SBO batteries.
4.0 Severe Natural Events for Which Plant Systems are
studied in this report:
Even
though sufficient margins have been built in, above DBFL, extended station
blackout has been studied deterministically. In case of water inundation upto
7.65m height there will not be any impact on the station as pump house grade
level is 7.65m and all other buildings are above this level. Hence, reactor can
be safely shutdown and long term core cooling can be ensured using the designed
systems in this scenario. In case of water inundation of above 7.65m height the
pump house and heat removal from the normal route will be affected. Turbine
will trip on low vacuum following loss of condenser cooling water and the plant
has to be brought to shutdown condition immediately.
In
a realistic scenario, there will be about 2 to 3 hours time available from
tsunami alert to shut down and cool down the reactors in a normal manner. Also,
the leak tightness of the buildings which houses safety system pumps, DG’s,
EPSS, safety train building (UKA) will prevent the safety systems from getting
submerged.
Possible
Tsunami occurrence can be known from:-
ü Tsunami and earth quake alerts from agencies and
proposed earthquake alert system.
ü Recording of seismic activity by the instruments >
0.025g
ü Pump house bay level showing unexpected changes
Event
progression in different scenarios up to a maximum of postulated event scenario
brought out above with mitigating actions:
4.1 Event progression if Group-III power is not available:
As
the water start rising above 7.65 m pump house will be submerged and all the
pumps like CCW, PGB, will be affected. As the DG building is not submerged,
Group II power will be available. The Essential Load cooling water pump house
is a sealed structure and is expected to be operable. Cooling to condenser will
be lost leading to fall in condenser vacuum and subsequently TG will trip on
low condenser vacuum. Reactor should be tripped manually if not tripped already
and Quick boron injection should be initiated;
ü Fast Steam Isolating Valves (FSIV) will close on SG
low level.
ü Start cooling of the reactor using PHRS and borated
water addition to RCS has to be started using Emergency Boron Injection System
(EBIS) -.
ü Primary system inventory make up by 1st stage
accumulators.
ü Reactor Auxiliary and Spent fuel pool cooling will be
affected.
ü Break the condenser vacuum and vent out hydrogen from
generator.
4.2 Event progression if Group-II Power becomes unavailable
For
this to occur, water should inundate up to 9.3 meter elevation and if no credit
is taken for the leak tightness of the buildings entire Group-III and Group-II
power supplies will be lost.
ü TG will trip, CCW pumps, FW pumps, RCPs will also
trip.
ü SG pressure will start rising resulting in opening of
atmospheric dump valves BRU-A.
ü Due to fall in SG level, Steam isolation valves will
close.
ü Cool down should be initiated immediately using all
four channels of PHRS.
ü Primary system inventory make up by 1st stage
accumulators.
ü Reactor Auxiliary and Spent fuel pool cooling will be
affected.
ü Break the condenser vacuum and vent out hydrogen from
generator.
ü As per the safety analysis carried out, primary
pressure is expected to reach 3.5 MPa and 165 deg C by 24 hours.
Under
the postulated scenario following systems become unavailable:
ü Group -III and Group-II power Supply Systems
ü All active safety systems
ü Sea water cooling system
ü Chemical and volume Control System (CVCS)
ü Spent Fuel Pool Cooling
ü Electric Fire Water Pumps
ü Normal and Emergency Ventilation System
Under
the postulated scenario following systems will be available;
ü Reactor Trip and CPSAR position Indication
ü Passive Heat Removal System (PHRS)
ü ECCS 1st Stage Hydro accumulators
ü ECCS 2nd Stage Hydro accumulators
ü Containment Isolation
ü Hydrogen Recombiners
ü Quick Boron Injection System (QBIS)
Under
the postulated scenario following Indication will be available for 24 hrs
through SBO Batteries:
ü Neutron Flux
ü Pressure above the core
ü Containment Pressure
ü Coolant Temperature
ü Hydrogen Concentration Inside the Containment
ü Reactor Coolant Level
ü Reactor Sump Level
ü Radiation Inside the Central Hall
ü Pressure Vessel Level
ü Coolant temp in hot and cold legs
ü Boiler water level
ü Temperature inside the Containment
Core
cooling will be available using PHRS provided sufficient water inventory in SG
is maintained. In case of leakages from the secondary side of SGs if the
inventory starts coming down provision is to be made make up the secondary from
outside the containment through hook up provisions to feed water line. During
this phase, Reactor Coolant inventory makeup is possible from 1st stage
accumulators and then from 2nd stage accumulators whenever pressure falls below
1.5 MPa. Considering a leak rate from the RCS as 5m3 per day and volume
shrinkage due to cooling as 100m3, inventories in 1st stage accumulator (4x60 m3)
alone is sufficient for more than 20 days. Further make up of RCS from 2nd stage
accumulators (8x120 m3) is available. Approximately 800 m3 of borated water is
available above the level of spent fuel assembly in the fuel pool for emergency
core cooling. Once the fuel pool cooling is not available water loss from the
fuel pool will take place due to evaporation. 4.2.1. Aspects to be addressed
under the scenario of Station Blackout concurrent with severe natural event After
detailed discussions, the minimum requirements to be addressed for core safety
and spent fuel safety for SBO condition extended beyond 24 hours has been
arrived at
a)
Provision for Makeup of water on secondary side of Steam Generators
b)
Provision for Make up of Borated water to Spent Fuel Pool
c)
Provision for Injection of borated water in the Reactor Coolant System at
required pressure in case any leakage develops and the existing substantial
back up inventories are exhausted.
d)
Hook up provisions from outside the Reactor Building for the above water
addition requirements from alternate sources other than the designed water
routes.
e)
Augmentation of onsite water resources/storage designed to be intact following
tsunamis/earth quake (with suitable capacity).
f)
Mobile pumping equipment/other methods that do not require on site or offsite
power
g)
Alternate Power sources for the mobile pumping equipment
h)
Monitoring of important parameters (under item 4.2 above) using portable power
packs at suitable pre identified wiring terminals.
4.3 Preparation of EOPs and training of operators:
It
is seen that draft version of EOP for tsunami, SBO and other BDBAs covered in
design are prepared. They have to be finalized and training of operators on
these EOPs is to be done.
5.0 Long term Recommendations:
i.
Provision of solar powered lighting for different buildings.
ii.
Study the feasibility of using wind power generator already available at KKNPP
site as a backup power.
6.0 Conclusion:
Review
of the core cooling capability of the KKNPP during a postulated beyond design
basis scenario of tsunami resulting in incapacitation of motive power and the
designed water supply route was carried out. It is seen that KKNPP design has
incorporated sufficient passive systems to ensure core cooling and radio activity
confinement even in the case of an extended unavailability of electric power
and the designed water supply route. Hydrogen management and molten core long
term cooling systems are also available to ensure the integrity of the
containment systems. Grade levels of all the main buildings have sufficient
margins from the design basis flood level which is conservatively arrived at.
However, as a means to further enhance the level of safety and to build more
defense in depth the committee recommends the implementation of the measures
outlined to cope up with unanticipated and rare severe and multiple natural
events having very low probability like the one that took place at Fukushima
Nuclear Plants in Sendai prefecture of Japan. The engineering details of these
additional measures are being worked out. The schedule (short term and long
term) of implementation will be submitted along with engineering details by end
August 2011
17 CONDIDITONS ON KKNPP TASK FORCE
REPORT AND REPLIES BY NPCIL, AERB RECOMMENDATIONS
S.No.
|
RECOMMENDATIONS
BY AERB
|
SCHEDULE
OF WORKS TO BE COMPLETED BY NPCIL BASED ON REVIEW AND RESOLUTIONS BY AERB
|
1.
|
Back
up provisions from alternate sources should be made for
–
charging water to secondary side of SGs
--
Make-up of borated water to spent fuel pools
--
Injection of borated water in the reactor coolant system
|
A
Seismically qualified 8000 m3 tank as an alternate backup water
source will be constructed (Short Term)
|
2
|
Seismic
qualififation of emergency water storage facility and augmentation of its storage
capacity for core decay ehat removal for a period of at least one week
|
Seismic
qualification of emergency water storage facility and augmentation as
required will be done progressively (Short Term)
|
3
|
Mobile
self powered pumping equipment for emergency use
|
Provision
of a mobile DG for emergency use will be made (Long term)
|
4.
|
Facility
for monitoring safety parameters using portabale pwer packs
|
Using
mobile DG and battery backed up portable measuring devices, safety parameters
will be monitored. (Long term)
|
5
|
Finalisation
of emergency operating procedures for BDBA conditions
|
EOPs
for some PIEs has been made Remaining are in progress (Short term)
|
6
|
Primary
containment to be assessed for ultimate load bearing capacity (ULBC)
|
Based
on design margins available, preliminary assessment shows that for primary
containment, ULBC is at least 1.5 times DBA value. The detailed analysis for ULBC will be done
progressively. (Long Term)
|
7.
|
Doors
and barrels of airlocks to be qualified for proof test pressure
|
The qualification of barrel and outer door
of TAL has been carried out by design analysis and meets the
requirement. Complied/
|
8
|
Ensuring
that highly active water used for cooling the core catcher vessel under BDBA
is contained inside the primary containment
|
The
required analysis is being carried out. (Long term)
|
9
|
Reconfirmation
of design adequacy of hydrogen management system
|
Design
adequacy of H2 management system has been reviewed and all aspects
are addressed. Complied.
|
10
|
Environmental
qualification of core catcher temperature monitoring system
|
The
instrumentation for core catcher monitoring has been qualified. Complied.
|
11
|
Adequacy
of design provision for remote water addition to core catcher
|
Water
addition provision through hook up point already exists and is adequate. Complied
|
12
|
Adequacy
of instrumentation for monitoring plant status during BDBA
|
All
important parameters of the plant during BDBA will be monitored. Provisions to extend power supply to these
instruments will be implemented progressively (Long term)
|
13
|
Details
of margin available on location of various safety related SSCs above DBFL
should be reviewed again.
|
Margins
have been reviewed and found adequate .
Complied.
|
14
|
Need
for design provisions for containment venting, that has been deleted, should
be reexamined.
|
Existing
design and procedures of KKNPP avoid containment over pressurization by
having long term decay heat removal system.
Complied
|
15
|
The
backup sources for water injection to SG secondary side should be seismically
qualified
|
Seismically
qualified water storage tank of 8000 m3 capacity will cater to
this requirement (Short term)
|
16
|
Provisions
for addition of water to core catcher require a detailed study, to ensure
that there is no possibility of any steam explosion.
|
Existing
design and procedures of KKNPP prevent possibility of steam explosion. Complied
|
17
|
Provisions
of additional backup power supply sources for performing essential safety
functions, like air cooled DGs located at a high elevation, should be
considered.
|
Provision
of mobile DG will be made for performing essential functions (Long term)
|
EOP:
Emergency Operation Procedures
PIE
: Post Irrdiation Examinations (Postulated Initiating Event)
TAL:
Tapped Anchor Location
SSC:
Structures, System and Component
DBFL:
Design Basis Flood Level
No comments:
Post a Comment