REPORT ON EVALUATION OF KUDANKULAM SITE FOR
LOCATION
OF 2 X 1000 MWe VVER NUCLEAR POWER PLANT
(from NPCIL reports, NEERI EIA report of 2003 for Kudankulam Nuclear plant)
http://www.aerb.gov.in/T/PUBLICATIONS/CODESGUIDES/S-8.PDF [siting criteria]
http://www.aerb.gov.in/T/PUBLICATIONS/CODESGUIDES/S-8.PDF [siting criteria]
1. INTRODUCTION
The acceptability of a site
for locating a Nuclear Power Plant is dependent not only on site
characteristics, related primarily and directly to safety, but also on a large
number of other aspects which are only indirectly related to safety. These include the reliability and stability
of the electrical grid, the adequacy of communications etc.
The siting of Nuclear Power
Plant (NPP) generally involves studies in three stages. Namely:
1) Site
survey stage: The purpose of a site survey is to identify one or more preferred
candidate sites after both safety and non-safety considerations have been taken
into account. This involves the study
and investigation of a large region. It results in the rejection of unacceptable
sites and is followed by systematic screening and comparison of remaining
sites.
2) Site
evaluation stage: This stage involves
the study and investigation of one or more of the preferred candidate sites to
evaluate their acceptability from various considerations and in particular from
the safety considerations. The
site-related design bases are established at this stage. Subsequent to this a preliminary safety
analysis report is submitted for clearance before site construction is started.
3) Pre-operational
stage: This stage includes studies and investigations of the selected site
after the start of construction and before the start of operation in order to
complete and refine the assessment of site characteristics and to confirm
assumptions made in the safety analysis of the reactor as a part of the final
safety analysis report. The base line
data on environment are also established at this stage.
The stage one is within the
scope of the work of the site selection committee. The present committee aims to have a
preliminary evaluation of the feasibility of a site mainly from safety
consideration and ensure that the plant site combination does not constitute an
unacceptable risk. However, in view of
the fact that some non-safety considerations may affect safety related aspects,
such items also have to be studied. It
is to be understood that the present committee has evaluated the site from
screening considerations. The site
related design parameters/bases are to be established at appropriate
stages. The review is based on the
available information on population and industrial growth and other proposed
facilities at and around the site in addition to safety related aspects like
seismo-tectonic environment, geology, hydrology, extreme meteorological
phenomenon etc. The site is evaluated
from the following consideration.
1. Effect
of the region of the site on the plant
2. Effect
of the plant on the region’
3. Population
considerations.
While the first of the above
factors decide the safety of the plant due to site related natural and
man-induced events, the second factor influences the potential radiological
impact from the plant on the environment.
Population consideration is important for emergency planning.
The acceptability of a site
for a particular NPP depends on the
existence of engineering solution to site related problems which gives
assurance that the proposed plant can be built and operated within acceptably
low risk to the population of the region.
IAEA guidelines (1,2) have
been kept in mind for the site evaluation.
2. REVIEW FOR THE SUITABILITY OF THE SITE AT KUDANKULAM
2.1 GENERAL CONSDIERATION
2.1.1. SAFETY-RELATED ASPECTS
Potential site-specific
natural hazards and man-induced events have been evaluated for initial
appraisal of their impact on the plant design and the engineerability under the
given circumstances. Subsequently these studies
form the design bases
Among the natural hazards, the
following aspects as relevant to site have been studied.
i)
Surface faulting
ii)
Seismicity
iii)
Suitability of subsurface material
iv)
Flood and
v)
Extreme meteorological phenomena (e.g. cyclone)
Because of rocky substrata
slope instability, soil liquefaction, surface collapse, subsidence or uplift
are not applicable for the present site.
Man-induced events include
accidents due to
i)
Air traffic
ii)
Vehicular road traffic
iii)
Industrial and Military activities in the
immediate vicinity of the site.
Capability of dispersion in
air and water are studied for possible radiological impact on environment. The
availability of adequate cooling water supply for the Ultimate Heat Sink is the
central safety issue. Feasibility of
implementing effective emergency actions has also been considered.
2.12 NON-SAFETY CONSIDERATIONS
(Economic, Technical,
Environmental and Social Aspects)
These are primarily related to
engineering feasibility. However, some
of the factors may indirectly be related to the safety of the NPP.
The factors considered are:
i)
Electricity network
ii)
Availability of cooling water
iii)
Transport routes
iv)
Topography
v)
Industrial support at site
vi)
Non-radiological impact on the environment (e.g.
chemical and thermal pollution, industrial growth and its impact etc.)
2.1.3. OBSERVATIONS OF THE
COMMITTEE
The committee has studied all
site related data submitted by NPC (3,4,5)and has, in accordance with the
criteria mentioned above, made a review of the suitability of the Kudankulam
site for locating a nuclear power station having two units of 1000 MWe VVER
reactor.
The review findings are
presented in Tables 1and II
3.ACTIONS TO BE TAKEN
The committee recommends that
the following actions should be taken at
appropriate stages.
3.1 Aspects related to site
1) ODC
committee of NPC to evaluate suitability of transportation of ODC at design
stage.
2) Maximum
Flood Level should be estimated accurately considering IAEA safety Gudie
50-SG-S10B. Revised report of CWPRS
should be submitted to Design Safety Committee
3) Analysis
for the quality of construction water is to be carried out
4) In
order to enhance additional reliability for water supply, which is essential
for functioning of various safety systems of the reactor, intake well at
Pechiparai Dam should be provided at lower elevation than the minimum draw-down
level of the reservoir. However, it
should be ensured by proper management of water distribution that the water
level is maintained above this minimum level.
5) Adequate
storage of fresh water for prolonged safe shutdown of the reactors is to be
provided within plant boundary for safety related systems. Ground water source should be explored.
6) Environmental
Survey Laboratory should be set up at site and instruments are to be installed
at site to collector meteorological data and background radiation.
7) Site
related design considerations such as seismic aspects, etc. are to be
established before submission of PSAR.
8) The
committee has been informed that detail subsoil investigations have been
carried out (12). Bore-hole investigations are to be carried out at the
proposed location of various buildings and structures. The report should be forwarded to design
group for taking into account at the time of actual design.
9) Power
evaluation studies particularly that influence the plant grid interaction
should be persued. Feasibility of
operation on islanding mode may be studied in collaboration with CEA. In addition availability of a reliable
dedicated startup power source of adequate capacity should be examined.
10) Stipulations
made by various state and central authorities in giving clearance should be met. In addition, plantation in the area under
control of the project should be taken up along with site development.
11) Tamilnadu
legislation to control population growth beyond natural growth within the
sterilized zone is to be implemented.
12) Termination
of the lease in 1994 for lime stone quarry.
3.2 ASPECTS
RELATED TO DESIGN:
1) Radiological
impact should be assessed with proper source terms and relevant dispersion
characteristics of the site. Dose limits
prescribed should be met at a distance
of 1.6km in the event of greater exclusion radius adopted by NPC
2) Stack
height to be checked by Health Physics Division, BARC considering topography
and dispersion characteristics.
3) Model
studies should be taken up for intake and outfall structure for thermal
pollution and recirculation.
4) Studies
on Biofouling and Jelly-fish etc. that may affect the water supply should be
take up.
5) Studies
on accretion/erosion rate around the plant site should be carried out. If required, proper protection should be
provided.
6) Design
should be engineered to meet site related design basis events.
7) At
least two evacuation routes from plant site during an emergency should be
provided.
4.RECOMMENDATIONS:
The committee is of the
opinion that Kudankulam site meets the major criteria for siting 2 x 1000MWe
VVER units. The committee at the same time recommends that the observations
made in the preface and the actions recommended in Section 3 above need to be
implemented at appropriate stages.
REFERENCES:
1. IAEA-code
of Practice on Safety in Nuclear Power Plant Siting. IAEA Safety Series No.50-C-S International
Atomic Energy Agency, Vienna, 1979.
2. Site
Survey for Nuclear Power Plants. IAEA
Safety Series No.50-SG-S9. International
Atomic Energy Agency, Vienna, 1984.
3. Environmental
Data on proposed Kudankulam site for submission to Tamilnadu Pollution Control
Board for 2 x 1000MWe VVER nuclear power station.
4. Write
up on Kudankulam site –DAE
5. Siting
data in AERB standard format. (Received from NPC vide letter NPC/KK/24/1032 dt.
7-3-89)
6. Layout
of main plant building for 2 x 1000 MWe
VVER project at Kudankulam.
Drawing No.KK/10,000/2001/GA/120.
7. CWPRS
Pune Report: “Safe Grade Elevation for the Proposed Nuclear Power Station at
Kudankulam, Tamilnadu”.
8. Draft
report on Earthquake Design Basis for Kudankulam site, DAE, 1988-AK Ghosh and
DC Banerjee.
9. Appendix
to Part-I of Site Selection Committee report.
10. Power
Transmission System for Kudankulam Atomic Power Project-CEA report.
11. Letter
NPC/KK/24 dated 16-3-89 received from NPC
12. Brief
note from NPC on “Geological setup of
Kudankulam site”
SALIENT FEATURES OF KUDANKULAM SITE
CONSIDERED DURING SITE EVALUATION
S.No
|
SITE CHARACTERISTICS
INFLUENCING THE NPP
|
SPECIFICATIONS/
DESIRABLE CHARACTERISTICS
|
OBSERVATIONS FOR KUDANKULAM
SITE
|
REMARKS
|
|
1.
|
TOPOGRAPHY
|
Plain Topography
|
Elevation +3 m to 45m above
MSL. Area measuring 1km x 2km
available (3) (6)
|
Terrain suitable Sufficient
land available for future expansion.
|
|
2.
|
ACCESSIBILITY
|
Recommendation for ODC
transport:
1)All
consignments/equipments with weight <30 p="p" ton:="ton:">
30>
USSR-Tuticorin:by ship,
Tuticorin-site:by road or on barges by sea route
2)All consignments > 30
tons USSR-site: by ship and barges. To
be unloaded at Jetty within the plant.
|
|||
i)Nearest Broad gauge rail
head
|
Kanyakumari (27 Km),
Valliyur (27km)
|
||||
ii)Nearest national highway
|
NH-7at Kanyakumari 27km,
Valliyur (27km)
|
||||
iii)Nearest sea port
|
Tuticorin (100km)
|
||||
iv)Nearest district road
|
Coastal road from
Kanyakumari
|
||||
3.
|
Construction Facilities
|
||||
i)Construction materials
|
Coarse agreegates available at
Anjugramam (4km) Sand available at Hanumanathyovari Road (7km) Bricks
available at Panagudi (27km)
|
More sources will be
established at construction stage.
|
|||
ii)Construction Power
|
26 MVA +2MVA for township
|
Panagudi substation (27km)
-110KV line exists
110KV line from Kodyar power
station is also being considered
|
Required power will be made
available.
|
||
iii)Construction Water
|
3.5 Cu.Sec (350 Cu.m per
hour)
|
Initially limited supply
tobe tapped from ground water sources.
Subsequently the demand will
be met from Pechiparai dam
|
Quality of construction
water is likely to be acceptable.
Analysis of water will be carried out.
|
||
iv)Infrastructure facilities
(e.g minor workshop etc.)
|
Nagercoil (30km) and
Tuticorin (100km)
|
||||
4.
|
Availability of Power Supply
and Transmission Lines
|
||||
i)Start-up power
|
60 MVA per unit
|
Available from main state
grid and Tuticorin Thermal Power Station (plant capacity 630 MWe) 220KV line
to be drawn from Tuticorin
|
|||
ii) Power evacuation scheme
|
Feasibility as per
preliminary study conducted by CEA. Detail study is in progress.
|
Present grid capacity 12832
MWe. Nuclear 470 MWe. Projected
capacity in 1995 will be 27541 MWe. Nuclear 1910 MWe.
|
|||
5.
|
Availability of Water
|
||||
i) Condenser cooling
|
6000 cu.sec (on once-through
basis)
|
Sea water cooling on
once-through basis.
Siltcontent:60-100ppm
Particle size:75 microns
Temp: 26-290C (5)
|
No constraint. Titanium tubes will be used.
Study on biofouling and jelly
fish that may affect the water supply will be taken at design stage.
Model study will be taken up
for intake and outfall structure (5)
|
||
ii)Fresh water for makeup
and domestic use
|
10 cu.sec
|
Assured by state Govt. One
pipe line from Pechiparai dam (at 65km) to be laid.
pH:7,
Dissolved solids:25mg/l
SS : negligible
Turbidity : 5 mg/l (5)
|
Dam storage 4.45 TMC Dead
storage can account for 3 years drought.
|
||
6.
|
Township
|
400 acres, 400 acres 7km from the site (3)
|
|||
Table-2
SITE CHARACTERISTICS - AFFECTING
SAFETY OF PLANT
S.No.
|
Site
Characteristics influencing the NPP
|
Desirable
Characteristics
|
Observations for
Kudankulam
|
Remarks
|
|||||||||||
1.
|
Geology
|
||||||||||||||
i)Foundation conditions
depths of bed rock and type
|
Bedrock at 5-16 m below
ground.
|
||||||||||||||
ii) Strength
|
Maximum intensity of loading
6kg/sq.cm at RB
|
Dry strength:650kg/sq.cm
Wet strength:450kg/sq.cm (5)
|
|||||||||||||
iii)Ground water
|
Below >1m
|
5-8m below ground gradient
towards Sea (5)
|
|||||||||||||
2
|
Natural Events
|
||||||||||||||
i) Coastal erosion
|
Erosion insignificant with
respect to life of station. Nearest
main plant structure from shore about 120m away from the sea base line.
|
Layout for the main plant
still under consideration. Figure of
120m estimate on the basis of 7m as the ground elevation at main plant
building.
|
|||||||||||||
ii)Flood
|
Maximum flood level
considering tidal range wave run-up and maximum storm surge 5.9 m above chart
datum of 0.0 (7)
|
Grade level of reactor above
7m from MSL after CWPRS report elevation will be changed if necessary
|
|||||||||||||
iii) Tsunami
|
Not significant as per CWPRS
|
1m height of wave considered
due to tsunami effect
|
|||||||||||||
iv)Wind, storm, cyclone
|
Storm speed: 112km/hr
Storm surge accounted .
Exceedance probability 5% as per CWPRS
|
Engineering capability to
design for wind load exists
|
|||||||||||||
v)Slope instability
|
Not applicable for rocky
substrata
|
||||||||||||||
vi)soil liquefaction
|
Not applicable for rocky
substrata
|
||||||||||||||
vii) Seismotectonic
|
No active fault within 5km
of NPP. Engineering capability for
stipulated earthquake acceleration should be possible
|
No active fault within 5km
Site is in seismic zone II
Epicenter at Trivandrum at 90km
PGA is 0.06g
|
Engineering capability to
design exists.USSR experts confirmed with ground checks.
|
||||||||||||
viii)site surface collapse
subsidence or uplift
|
Not applicable to rock
substrata
|
||||||||||||||
ix)Failure of cooling water
supply
|
|||||||||||||||
a)Fresh water pipe rupture
|
Storage for safety related
system will be provided for prolonged safe shut down of reactor (5)
|
Plant operating procedurs
and pond capacity will be decided to ensure water requirement for decay heat
removal from the 2 units for a prolonged period. Ground water source will also be explored
as standby back-up arrangement.
|
|||||||||||||
b)Failure of upstream dam
|
Flooding not of consequence
as site is far away (50km) and the site is not in the course of the main
channel. Intake well at Pechiparai dam to be provided and supply to be taken
from upstream Kodyar storage for extreme contingency. Site storage is to be provided for safety
related systems.
|
||||||||||||||
3)
|
MAN-INDUCED EVENTS AFFECTING
SAFETY OF THE PLANT
|
||||||||||||||
i)Aircraft impact
|
|||||||||||||||
a)Nearest Airport
|
SDV 8km
|
Trivandurm (90 km)
|
|||||||||||||
b) Nearest Air Strip
|
SDV 4 km
|
-do-
|
|||||||||||||
c)Military Airport
|
SDV 15 km
|
-do-
|
|||||||||||||
ii)Toxic gas release
|
SDV 5 km
|
No industry using explosives
or having potential for explosion within 10km
|
|||||||||||||
iii)Chemical explosion
|
SDV 5 km
|
No industry using explosion
or having potential for explosion within 10km
|
|||||||||||||
iv) Industrial or military
accident
|
No industry or military
establishment within 10km
|
||||||||||||||
v)Surface vehicle impact or
explosion
|
No national highway or
railway siding within 10km. Coastal
road from Kanyakumari to Tuticorin is about 4km from the site
|
||||||||||||||
4
|
METEOROLOGY
|
||||||||||||||
i)Wind speed and direction
|
Observation at Kanyakumari:
Variation of daily average Velocity:6-30km/hr.
Direction: From West (44.5%
and NE (16.2%)
|
||||||||||||||
ii)Rain
|
Annual average rainfall:
810mm
|
||||||||||||||
iii)Atmospheric Temperature
|
Monthly avg:23-33oC
Extreme:19.2-36.8oC
|
||||||||||||||
iv)Humidity
|
Monthly avg:65-80% RH Extreme:60-85%
RH
|
||||||||||||||
v)Atmospheric stability
|
Environmental survey laboratory
will be set up to study.
|
Instruments will be
installed.
|
|||||||||||||
5
|
USE OF LAND
|
Exclusion zone: 34% of area
lies in sea. Remaining 650-750ha. Of land (no forest), mostly private owned
is baren and unirrigated /poorly cultivable. 60% area within 10km lies in sea. A
lime stone quarry of about 70 acres falls within the sterilized zone. The lease for this area expires in 1994.
Termiantion of the lease beyond theperiod has been requested.
|
|||||||||||||
6.
|
USE OF WATER
|
Ground water is limited and used for drinking and has a gradient
towards the sea. No salt pans within
5km. fisheries development is as common as in coastal belt
in the area of Idinthakari, Koothapuzh.
Fishing harbor is being developed at a Kanyakumari. 4000 tonnes is available. (4)
|
|||||||||||||
7.
|
DISPOSAL OF RADIOACTIVE WASTE FROM THE NPP
|
||||||||||||||
i)Solid Waste
|
Low level solid waste to be
buried within exclusion zoneinleak-proof RCC valults/trenches/tile
holes. 160-180m cu./year of cemented
waste including spent absorption materials, 40m cu/yr of compacted waste and
5m cu/y of cemented ash will be generated from one reactor. (5)
Bore wells surrounding the
solid waste burial area will be provided for monitoring migration of
activities.
|
||||||||||||||
ii)Liquid waste
|
To be diluted to 2 x 10E-7
micro Ci/ml when discharged into sea
|
Most of the radidoactivity
in the liquid is removed in the Ion Exchange resin and as evaporator concentrate. After above processing the liquid effluent
from two units is estimated as 6000m cu/year with activity levels lesser or
equal to 10E-9 ci/l. This will be
further diluted by condenser cooling water to meet the limits allowed by AERB
|
6000 cusecs of sea water
available for dilution while sea water less than 1 cusec required to achieve
the specified limits.
|
||||||||||||
iii)Gase release
|
Stack height is 100m. Use of high efficiency (0.3 micron)
particulate absolute filter will help to comply with authorized limits for
particulate activity. The estimated
gaseous discharges from 2 units as following.
It is understood that
specific detailed information regarding waste and radioactive releases will
be available along with PSAR for review
|
||||||||||||||
8
|
RADIOLOGICAL IMPACT
|
||||||||||||||
i)During normal operation
|
AERB
|
Based on releases vide
para7, preliminary estimates indicate very low dose rates 11.24 mrem/yr to
the individual at 1.6km exclusion radius.
Both the water and air routes have been considered in the above
estimates.
|
|||||||||||||
ii)During design basis
accident conditions
|
10rem: for whole body, 50rem
for child thyroid at exclusion radius
|
For all design basis
accidents adequate engineering safety features shall be provided to meet the
specified requirements
DBA calculations will be carried
out at the design stage.
|
|||||||||||||
9
|
THERMAL POLLUTION
|
Not significant. Intake and outfall will be well
separated. Depth of sea water and
large dilution due to sea will avoid thermal pollution
Model studies will be
carried out at CWPRS Pune. The
requirements of TamilNadu Pollution Control Board should be met.
|
|||||||||||||
10
|
STORAGE AND TRANSPORTATION
OF FRESH AND SPENT FUEL
|
Space for storage of fresh
fuel for 5 years plus one core charge will be provided. Each unit layout can store spent fuel of 5
ractors years in the spent fuel poor located inside the containment. Besides this, space will be available to
unload one core inventory.
|
50 Tonne of spent fule will
be discharged annually from the two reactors.
After adequate cooling inside thepool, it will be shipped to Soviet
Union by sea route in hermatically sealed casks. Special jetty provided withinthe plant area
will be used for transfer of cask to the soviet ships so that spent fuel
remains within plant boundary at all stages during the process of shipment of
irradiated fuel.
|
||||||||||||
11
|
FUEL REPROCESSING FACILITY
|
Reprocessing not planned at
this site.
|
|||||||||||||
12.
|
POPULATION CONSIDERATIONS
|
||||||||||||||
i)Population within 2km
radius exclusion zone
|
No habitation
|
No resident population
|
|||||||||||||
ii)Population within 5km
radius sterilized zone
|
Lessthan 20,000 population
density <2 average="average" p="p" state="state">
2>
|
Total population:15,000
3 villages in this area
Kudankulam, Idinthakarai and Erukkanthorai
|
Tamilnadu legislation to
control population growth beyond natural growth within the sterilized zone to
be implemented.
|
||||||||||||
iii)Population within 10km
radius zone
|
No center >10000
|
No population center with
more than 10000 people, Total
population 40,842 (1981 census) Population density 130 per sq.km
|
|||||||||||||
iv)Population within 30km
radius zone
|
No centre >1,00,0001
|
No population center with
more than 1 lakh people. 11 centers have population morethan 10,000. Nagercoil (at 30km) has a population of
1,71,641
|
|||||||||||||
v) Population within 50km
radius
|
33 population centers with
population more than 10,000 (4)
|
||||||||||||||
13.
|
EMERGENCY PREPAREDNESS
CONSIDERATIONS
|
3 routes for possible
evacuation. Schools andother public
buildings exist for adequate temporary shelter.
Nagercoil (30km) Tirunelveli
(100km) and Tuticorin (100km) can provide communication medical facilities
and administrative support
|
Draft proposal on off-site
emergency preparedness plans already submitted to AERB
|
||||||||||||
14
|
ADDITIONAL STATUTORY
REQUIREMENTS OF THE CENTRAL AND STATE GOVERNMENTS
|
Clearance for the following has
been obtained:
Tamil Nadu Pollution Control
Board
Shore Protection Committee
of TN Government
State Committee on
Environment,
Ministry of Environment and
Forests (Government of India)
Stipulation made in the
clearance documents should be adhered to.
|
|||||||||||||
This is the retyped version of original report, slightly modified
Retyped version checked by
VR Rajagopalan, ACE-LWR Design MC Barman, ACE-Civil KKHA
May 2012
2 comments:
Good Information - Keep it up
Indian agg - blogillu
India should be a union like european union where each state become a country and have sovereign power to decide its fate. Punjab,Tamil Nadu, UP, Maharashtra, Assam, and all other states when become a country can have a better administration and progress. It is obvious a few politicians in central cannot administer and fulfill wish of 1.2 billion people. Kudankulam is a clear case of central governments dont understand the wish of the local people. While keeping a lot of central power, they couldnt provide simple electricity/water supply peacefully agreeable to the locals without problems/corruption. Decentralize and distribute the administrative, executive and judicial power,then each state can look after their problems much better.